Sixth online Gradirnik: 155 attendees, three cases and a 5 MW plant
The sixth online Gradirnik webinar drew 155 attendees and worked through three cases: pharmaceuticals, food processing and packaging manufacturing. It was hosted by Maxim Krasnov, CEO of Cold Energy (NCT) and member of the International Academy of Refrigeration. For each case he showed which equipment and engineering solutions were selected for the plant's task.
Which cooling methods were discussed?
-
wet cooling towers and free cooling;
-
absorption chillers driven by a boiler house, and trigeneration;
-
thermal energy storage and load-following control;
-
adiabatic pre-cooling and water treatment.
What was compared for a 5 MW cooling plant?
For a 5 MW cooling plant, the webinar broke down where the costs come from:
| Cost item | What was included |
|---|---|
| Capital | equipment cost |
| Operating | electricity, water |
| Service | maintenance and repair |
What else was on the agenda?
-
six questions to ask yourself before choosing a system;
-
six mistakes plants pay for every year;
-
seven ways to save, summing up the whole review;
-
answers to attendees' questions.
Where can I watch the recording and get the slides?
The webinar recording is on Rutube (in Russian). The slides are in the Telegram channel "Maxim, we need cooling!"; details are in the news item about the slides. A diagram for choosing a cooling system with costs taken into account can be requested on Telegram from @Nct_admin.